Section 01001

    • 5.

      Provide opening in elements of Work for penetrations of mechanical and electrical Work.

  • D.

    Cut masonry and eoncrete materials using masonry saw or core drilL Restore

Work with New Products in accordance with requirements of Contract Documents.

  • E.

    Fit Work tight to adjacent elements. Maintain integrity of wall, ceiling, or floor construction; eompletely seal voids.

  • F.

    Fit Work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.

  • G.

    Refinish surfaces to match adjacent finishes.

SUBMITTAL PROCEDURES

A

B.

C.

D.

E.

The Contractor shall provide descriptive submittal packages as required by this section and as described in the individual sections of these Technical Provisions. No partial submittals will be accepted. Submittal form to identify Project, Contractor, Subcontractor or supplier, and pertinent Contract Document references. Apply Contractor's stamp, signed or initialed, certifying that review, verification of Produets required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents. Identify variations from Contract Documents and Product or system limitations, which may be detrimental to successful performance of the completed Work. Revise and resubmit submittals as required; identify all changes made since previous submittal.

SHOP DRAWINGS

A

Shop Drawings for Review:

].

Submitted to Arehitect/Engineer for review for the limited purpose of checking for conformance with infonnation given and the design concept expressed in the Contract Documents.

B.

Shop Drawings for Information:

  • 1.

    Submitted for the Architect/Engineer's benefit as contract administrator or for the Owner.

  • 2.

    Reports ofinappropriate or unacceptable work may be subject to action by the Architect/Engineer or Owner.

  • 3.

    Submit the number ofopaque reproductions, which Contractor requires, plus three copies, which will be retained by Arehitect/Engineer.

PRODUCT DATA

A

B

.

Submit the number of copies, which the Contractor requires, plus three (3) copies, which will be retained by the Architeet/Engineer. Product catalog data shall contain standard printed information on materials,

products and systems that shows perfonnance characteristics, controls, sequence of operation, dimensions, materials of fabrication and other characteristics

3 Section 01001