Year(s) Project Duration Project Status Name of Client Name of Project Cost of Project

: 1984 - 1985 : 9 Months : Complete : National Guard : Military School Project Riyadh with Al Trajmi Est. : SR 3,159,000.00

Project Description : Water tanks, water sewage line, concrete slab paving, building works & street lighting.

Year(s) Project Duration Project Status Name of Client Name of Project Cost of Project

: 1984 - 1985 : 12 Months : Complete : Water Department, National Guard : Pipe Laying Project for National Guard Building. : SR 774,000.00

Project Description : Water pipe laying.

Year(s) Project Duration Project Status Name of Client Name of Project Cost of Project

: 1984 - 1985 : 14 Months : Complete : Ministry of Communication : Riyadh Majammah Highway Project with ARTEC Co. : SR 12,000,000.00

Project Description : Road works, ditch & dikes.

Year(s) Project Duration Project Status Name of Client Name of Project

Cost of Project

: 1985 - 1986 : 6 Months : Complete : National Guard : Construction of Gate Boundary Fence of Imam Mohd.Bin Saud National Guard. : SR 1,547,000.00

Project Description : Gate fence works & street lighting.

Year(s) Project Duration Project Status Name of Client Name of Project Cost of Project

: 1985 -1987 : 28 Months : Complete : Port Authority : DUBA Port Project with Al Saady & Hyundai Engineering Co. : SR 34,000,000.00

Project Description : Wadi diversion canal construction & all civil works, 55000 cubic meters ready mix concrete supply.