Cost of Project

: SR 3,000,000.00

Project Description : Earth work, asphalt work, street lighting, curbstone & tiles.

Year(s) Project Duration Project Status Name of Client Name of Project

: 1991 - 1992 : 1 Year : Complete : Moda GDMW Hafar Al Batin : Design & Execution of Dual Carriage Way of King Khalid

Cost of Project

Military City Hafar Al Batin. : SR 43,000,000.00

Project Description : Earth work, asphalt work, road signage and painting, complete road project from design to road signage & painting

Year(s) Project Duration Project Status Name of Client Name of Project Cost of Project

: 1991 - 1992 : 6 Months : Complete : Moda : Construction of Diamond Interchange. : SR 16,000,000.00

Project Description : Construction of diamond interchange (bridge on majmaah to hafar al batin highway.

Year(s) Project Duration Project Status Name of Client Name of Project Cost of Project

: 1991 - 1993 : 2 Years : Complete : MODA GDMW : Moda Al Kharj Projects 201 with Bouygues (France). : SR 35,000,000.00

Project Description : All civil works mech., electrical works of 4,000,000 lm construction of encased power ducts, 240m/holes, 1200 road lighting poles, 120 substations, site development, etc.

Year(s) Project Duration Project Status Name of Client Name of Project

Cost of Project

: 1989 - 1993 : 4 Years : Complete : Ministry of Health : Civil Work Pipe Line Concrete Road Pavement Subcontract with Hyundai Engineering Co. GAHOS Project. : SR 25,000,000.00

Project Description : Concrete road pavement earth work water sewer & storm lines hard standing perforated pipes at three hospitals in Riyadh, hauta and hureymla.

Saudi Al Terais Co. - STICCO