Chapter 11 Soils & Foundations

CHAPTER 11 SOILS AND FOUNDATIONS

SICC-1101 GENERAL

SICC-1101.1 Scope. The requirements of this chapter and NCSBC-1704.7, NCSBC-1704.8, and NCSBC-1704.9 shall apply when construction includes soil-related conditions or foundation systems as listed in SICC-302.7.

SICC-1101.2 Soils report. The soils report as required by NCSBC-1802.2 and NCSBC-1802.6 shall be prepared, signed and sealed by the GER and shall be submitted to the CCBSD for review and approval with the construction documents. The GER approved soils report shall be used by the SIER to conduct special inspections during construction.

SICC-1102 FABRICATION AND ERECTION DOCUMENTS

SICC-1102.1 Review and approval. The soils and foundations fabrication and erection documents shall be submitted to the GER, SER for review and approval prior to construction, as appropriate. The GC shall provide GER/SER-approved fabrication and erection documents for use by the SIER to conduct special inspections during construction.

SICC-1102.2 Preparation of fabrication and erection documents. A RDP with experience in the design of deep foundation elements shall prepare, sign and seal fabrication and erection documents for pile and pier foundations. The fabrication and erection documents for cast-in- place concrete shallow foundations shall be prepared as required in SICC-2007 Chapter 7.

SICC-1103 SOILS-RELATED DEVIATIONS AND REVISIONS

SICC-1103.1 Review and approval. Three sets of revisions to the County approved soils report and/or the County approved construction documents that bear the seal and signature of the appropriate RDPs and shall be submitted to the CCBSD, as appropriate, for review and approval prior. The CCBSD shall determine if the construction can proceed pending approvals.

SICC-1103.2 Preparation of revisions. The GER shall prepare, sign and seal revisions to the County approved soils report if on-site soil and/or ground water conditions vary materially from those presumed to exist based on the initial subsurface exploration and as indicated in the approved soils report. The GER shall coordinate revisions to the County approved construction documents with the SER responsible for structural design of foundations and the RDP responsible for deep foundations, if applicable. The SER and/or the RDP responsible for deep foundations, if applicable, shall prepare, sign and seal revisions to the County approved construction documents. The GC shall provide GER/SER-approved revisions to the fabrication and erection documents for use by the SIER to conduct special inspections during construction.

SICC-1104 SPECIAL INSPECTIONS

SICC-1104.1 Soils. Special inspections as specified in the County approved Statement of Special Inspections shall be conducted to determine compliance with the GER approved soils report and the approved construction documents. The SIER or GER shall perform special inspections of soils in accordance with NCSBC-1704.7 and NCSBC-1803. Special inspections shall include:

Page 46