Appendix C General Contr actor Guide

APPENDIX C General Contractors Guide

The GC shall coordinate the scheduling of special inspections with the SIER and maintain copies of all Daily Field Reports as well as Descrepancy Reports on site for Building Officials review as needed. CCBSD will provide clipboards and blank forms for this purpose.

Footing Inspection. The following information shall be provided to the building official prior to requesting a footing inspection or monolithic slab pour:

  • Completion of Soil-Related Special Inspections SICC 1105.1.

  • Completion of Earth Retention Systems SICC 1205 (if system provides a bearing plane for the building).

  • Completion of Deep Foundation Inspections SICC 1105.2 (Piles & Cassions).

  • Cast in place Concrete - Daily Field Report or Monthly Engineer’s Summary addressing Material Certification, Reinforcement Installation, Welding of Reinforcement, Anchor Rods and Bolts, Concrete Form Work.

Footing inspections shall be made after the trenches are excavated, all grade stakes are installed, all reinforcing steel and supports are in place and appropriately tied, all necessary forms are in place and braced and before any concrete is placed.

Under Slab Inspection. Under slab inspections, as appropriate, shall be made after all materials and equipment to be concealed by the concrete slab are completed with appropriate verification tests if applicable.

Foundation Inspection, Crawl Space. The following information shall be provided to the building official prior to requesting a foundation inspection for a crawlspace installation:

  • Completion of Shallow Footings and Foundations SICC-1105.3.

  • Completion of Precast Concrete Construction Section 805.

  • Completion of Cast in Place Concrete Construction SICC-705 (If foundation walls are

poured concrete).

  • Completion of Masonry Construction Section 1005.

Foundation and crawl space inspections shall be made after all foundation supports are installed. This inspection is to check foundation supports, crawl space leveling, ground clearances, and positive drainage, waterproofing and dampproofing as required.

Rough-In Inspection. The following information shall be provided to the building official prior to requesting a rough-in inspection for parts of the electrical, plumbing, fire protection, or heating- ventilation or cooling system:

  • Completion of Sprayed Fire Resistant Materials SICC 1404.

Rough-in inspections shall be made when all building framing and parts of the electrical, plumbing, fire protection, or heating-ventilation or cooling system that will be hidden from view in the finished building have been placed but before any wall, ceiling finish or building insulation is installed.

Building Framing Inspection. The following information shall be provided to the building official prior to requesting a rough building inspection:

  • Completion of Shallow Footings and Foundations SICC-1105.3.

  • Completion of Cast in Place Concrete Construction SICC-705.

Page 75