X hits on this document

137 views

0 shares

0 downloads

0 comments

6 / 57

a) If the concessionaire is selected through ICB

The concessionaire is free to procure the goods, works, and services required for the facility using its own procedures

The Loan Agreement specifies the type of expenditures incurred by the concessionaire to which World Bank financing will apply

OR

b) If the concessionaire is not ICB selected, the goods, works, or services required for the facility and to be financed by the World Bank should be procured through ICB

Procurement under BOO/BOT/BOOT Concessions with the World Bank Participation

Document info
Document views137
Page views137
Page last viewedFri Oct 28 20:24:06 UTC 2016
Pages57
Paragraphs605
Words3868

Comments