2003 SPECIFICATIONS

SECTION 108

DEPARTMENT LETTERHEAD (Date)

RE: STATEMENT OF TIME CHARGED JOB NO. FAP NO.

(Contractor) (Contractor Address) Dear Sir:

During the Estimate Period ending (date), time was charged on the above project on the following

dates:

Monday, 6-2-99 Tuesday, 6-3-99 Thursday, 6-5-99 Friday, 6-6-99 Monday, 6-9-99 Tuesday, 6-10-99

Days Charged This Period:

6

Days Charged Through (Est. Period Ending Date)

85

Total Contract Time

200

Please review these time charges. In accordance with Subsection 108.06(c) of the Standard Specifications, if you do not file a written notice of disagreement and the reasons therefor within ten (10) calendar days from your receipt of this letter, you will be deemed to have accepted the time charged for this period as correct, and no subsequent request for review will be considered.

During this Estimate Period, the following dates were assessed as Site Use days:

Monday, 6-2-99 Tuesday, 6-3-99 Wednesday , 6-4-99 Thursday, 6-5-99 Friday, 6-6-99

OR June 1 - 6, 1999, inclusive

5 days

Site Use Days Charged This Period: Site Use Days Charged Through (Est. Period Ending Date): Total Site Use Time:

5

42 120

Yours truly,

Resident Engineer

cc: file

FIGURE 108-4

Page 100-97