2003 SPECIFICATIONS

SECTION 108

PROCEDURE FOR COMPLETION OF THE SITEMANAGER DAILY WORK REPORT

  • 1.

    Job Number

  • 2.

    Inspectors Name (automatically inserted)

  • 3.

    Date

  • 4.

    Authorized Indicator – Yes indicates that the DWR has been authorized and cannot be

changed by the inspector.

  • 5.

    Authorized Date: the date that the DWR was authorized by the Resident Engineer.

  • 6.

    High temperature for the day.

  • 7.

    Low temperature for the day.

  • 8.

    & 9. Morning and afternoon weather conditions. Inspector selects the appropriate condition

from a drop down list. 10. Indicator Boxes: a check mark in the box beside each statement indicates that the statement is true. The check marks automatically clear as the inspector enters appropriate information. 11. Work Suspended: If the work on the project is suspended by the contractor due to adverse weather conditions or other factors, the inspector must check the box beside the statement and enter the time (in military time) that the work was suspended. 12. DWR Remarks. The minimum required remarks for each day are:

Working Conditions NOTE: If “Poor”, Inspector should state why conditions are Poor. Time Charged (Yes or No) Engineering Activities Contractors Work – Roadway Contractors Work – Structures (See the Inspectors Guide for further instructions on the use of Contractors Work – Roadway and Contractors Work - Structures. Also, see Subsection 110.03 of this Manual for use of the “Erosion and Sediment Control Field” Remark Field)

13. 14.

Contractors Tab - Show the contractor and

&

15.

Contractor

Supervisors

and

subcontractors working on Personnel Types (job

the project on that day. classifications) – It

is

not

necessary to keep the inspector will potential claim for

up with the contractor’s supervisors and personnel on a daily basis; however, keep up with this information when the Department is put on notice of a changed conditions, or as otherwise directed by the Resident Engineer.

15A. DWR Preview Button daily work report, as shown in 16. Contractors Equipment

  • clicking on this icon provides a printable summary of the entire

Figures 108-10 and 108-11. Window – At least once per week, and when significant changes

occur, show the major equipment present on the project the number of units in use that day. If the inspector is

for each contractor and subcontractor and aware of any equipment broken down or

otherwise not in operable condition, a Inspectors Guide for specifics regarding the Contract Masterlist. 17. The quantity of a specific model/type

remark should be recorded to that effect.

See the

the

listing

and

recording

of

contractor’s

equipment

in

of equipment that is on the job site that date.

  • 18.

    The quantity of the above equipment that is actually in use that day.

  • 19.

    The combined total hours that the specific pieces of equipment were

CAT D-4 bulldozers worked for 8 hours. Total hours used=24 hours). 20. Daily Staff Tab- The inspector shows all Department personnel (and

used that date (i.e. 3

consultant inspection

personnel

if

applicable)

working

on

the

project

that

date.

Entries

are

not

required

for

Work

Code,

Regular Hours, Overtime, and Vehicle Number and Mileage are not required at this time. 21. DWR Select Work Item Window- A check mark in the installed column indicates entry has been made by the inspector for that item.

that

an

Figure 108-6 Daily Work Report (continued)

Page 100-105

Rev. 12-14-04