X hits on this document

851 views

0 shares

0 downloads

0 comments

62 / 220

2003 SPECIFICATIONS

SECTION 107

installing a side drain, constructing a curb section, or constructing the driveway) should be kept to the minimum necessary to complete the work.

(e) Control of Livestock. The Contractor is required to provide such fencing as needed to contain livestock adjacent to the project limits until such time as permanent fencing is installed. Permanent fencing is fencing that is installed in its final location and will not be disturbed by construction operations for the remainder of the contract. All

other fencing is considered temporary fencing and shall not be paid for unless specifically provided for in the contract. There are no specifications temporary fence; however, it must be adequate to control the livestock.

payment is governing

107.03 Restraining Conditions. (a) Department R/W. Unless otherwise stated

on the plans, all known environmental clearances needed obtained for Department Right-of-Way during the plan construction, continued monitoring of all work will be done

for a project will have been development stage. During by the Resident Engineer and

his Staff. If a Specifications,

Restraining Condition, as defined in Subsection 107.10 of the Standard is encountered, the Resident Engineer shall notify the Environmental

Division and be stopped

the District Engineer immediately. until a further determination is

At the

same time, work

at that site

shall

made

by Department

personnel.

The

Environmental Division will document the disposition of the site by memorandum to Construction Office for distribution. Project work may continue in areas not affecting

the the

material at the site in question. (b) Off-Site Locations.

Section 107.10 of the Standard Specifications

requires environmental clearances for ALL project related off-site locations used by the Contractor. This includes borrow pits, haul roads, waste areas, equipment storage areas, etc. Commercially operated pits or quarries, as defined in the Specifications, must also have environmental clearances; however, the owner/operator of the commercial site is responsible for obtaining the clearances.

To facilitate obtaining the required clearances, the following procedure will be

used:

(1).

The Contractor should submit to the Resident Engineer a separate

“Restraining Condition Clearance location before commencing any

Request” form (Figure 107-2)

site

preparation.

This

form

is

for each available

off-site on the

Construction drive of the LAN (CSD4:\misc\clr-frm2.doc). As part of Contractor will prepare a location map of the proposed off-site location Quadrangle map in sufficient detail to enable anyone to look at the proposed site, and survey the area.

this request, the on a 7.5 minute sketch, find the

(2). The Resident Engineer should review the site to ensure it has been staked sufficiently to locate it and that no site work has been performed. The Resident Engineer shall fax the sketch and “Restraining Condition Clearance Request” form directly to the

Environmental

Division

Environmental

Division.

(FAX No. These actions

501-569-2009) and should be handled as

mail the original form expeditiously as possible.

to

(3).

The Environmental Division will notify the Resident Engineer of the

disposition of the site request document it by completing

(approval or disapproval) within 10 business days and will the remainder of the “Restraining Condition Clearance

Page 100-47

Rev. 5-03-05

Document info
Document views851
Page views851
Page last viewedTue Dec 06 20:18:55 UTC 2016
Pages220
Paragraphs6755
Words74435

Comments