The Carve Out Process – Overall schedule

Ò The Carve Out of Nordenham, Varel and Augsburg and the integration into the NewCo had to be done in three main steps:

Step:

Date:

Activity:

management of

transferred into

depending on

NOR/VAR/AUG

NewCo

ERP are

NewCo set up & operational Management

NOR/VAR/AUG legal Transfer into the NewCo

01/09/2008 01/01/2009 Ò Foundation of NewCo

Ò NewCo takes over operational

Ò NOR/VAR/AUG will be

implemented

Ò Projects depending on ERP are implemented

Full ERP Separation

11/04/2009

Ò Full ERP separation

Ò Process changes

(Betriebsführung)

Ò Augsburg is still part of Military Air Systems

Ò NOR/VAR are still part of Airbus Germany

Ò All carve out Projects are implemented (e.g. TSA’s, WPA’s)

01/09/08

01/01/09

11/04/09

NewCo Operational Management

NOR/VAR/AUG legal transfer into the NewCo

Full ERP Separation