6.7.1 Action Plans/Programmes for Development Cells (Using Cell T3 as a Model)

Development Agency in co-operation with, and under supervision of relevant authorities will be responsible to the relevant authorities for preparing detailed layout plans, for arranging pre-financing of the construction of services (to be recovered from concessionaires through revenues raised on land values and consumption of services)

A mix of the above options could be applied to any particular area.

For future development of development cells or areas two options are presented below. One is where a whole cell or area is parcelled out to a single developer under one concession on a tender basis as previously described (see Table 14). The developer would then be responsible for elaboration of the detailed layout plan within the overall guidelines of the IDP, and for investing in and arranging the construction of internal services. In the other option lots are allocated to individuals

Note:

the conditions as

subject to

each under its own concession and

the

case

this

In

15).

Table

(see

elsewhere

defined

Development Cell T3 – Single Developer Option

Table 14

TIMEFRAME

RESPONSIBLE ORGANISATION

ESTIMATED COST (WHERE AVAILABLE)

FINANCED BY

ACTION

STEP

Short to medium term

Development Agency in co- operation with relevant authorities

15 000 USD

Initially from funds generated through levies on land value of concessions and other development revenues as described in other sections above

Elaborate infrastructure investment/development programme departing from the preliminary projects proposals

Assess the value of the land and prepare tender documentation for bids for new concessions(Including criteria for adjudication of bids)

Prepare legal, technical and other documents required to facilitate development of the area

Define development control measures, including for the monitoring of development proposals to ensure that they comply with IDP guidelines, and that developers contribute a fair share of the cost of general development of the area within reasonable timeframes

1.1

1.2

1.3

1.4