Action Plan/Programme for Cell T4 – Partly Concessioned, Partly Vacant Land – Developer Option

Table 16

TIMEFRAME

RESPONSIBLE ORGANISATION

ESTIMATED COST (WHERE AVAILABLE)

FINANCED BY

ACTION

STEP

Immediate (2 months)

Responsible authorities (local, district and provincial)

---

---

Adoption of the redesigned layout of concessions by responsible authorities.

1.1

Short term

Responsible authorities with help from Development Agency

8 000 USD

Municipality (from revenues)

Marking of sites: Preparation of documents with co-ordinates according to new layout

(Pegging and registration of sites to be done by developers as the need arises at time of construction start-ups)

1.2

Short term

Development Agency reporting to authorities for decisions

3 000 USD

Municipality (from revenues)

Elaborate infrastructure investment/development programme in phases, departing from the recommendations contained in sectoral reports for roads, water, sewage and solid waste disposal.

1.3

Short term (3 months)

Development Agency

10 000 USD

Grant funding (government and/ or private donors)

Evaluation of existing concessions to eliminate speculation and ensure serious development on the basis of the infrastructure investment programme and other requirements.

1.4

Short term (3 months)

Development Agency

To be included in

10 000 USD of 9.4

Grant funding (government and/ or private donors)

Develop tender procedures for vacant land, using land value as basis to secure contributions from developers towards development costs

1.5

122