DEMONSTRATION ACTIVITIES – Xai-Xai IDP

FAO-PAP/RAC-MICOA

Action Plan for Praia Velha Demonstration Project Implementation

Table 21

TIMEFRA ME

RESPONSIBLE ORGANISATION

ESTIMATED COST (where available)

FINANCED BY

ACTION

STEP

Completed

Joint PAP/RAC MICOA team

10 000 USD

Sponsored by FAO

Elaboration of detailed layout plan

2.1

Completed

Joint PAP/RAC MICOA team

10 000 USD

Sponsored by FAO

Elaboration of preliminary execution projects relevant to the detailed plan

2.2

Adopted in the end of 1998

Responsible municipal departments and city council

-

-

Adoption/approval of the plan by responsible authorities (Steering committee and Municipality)

2.3

Pegged in February 1999

“Provisional” Development Agency (SUIMO)

15 000 USD

Sponsored by FAO

Concessionaires

Marking of sites:

Preparation of diagrams with co-ordinates Pegging of sites Registration of titles

- - -

2.4

3 months

SUIMO reporting to city council for decisions

2 000 USD

Municipality and concessionaires

Elaborate the criteria and propose to the municipality guidelines for eliminating concessionaires who are not able or willing to contribute to the cost of developing infrastructure services

2.5

Short term (3 months)

Responsible municipal departments(with assistance of Development Agency if required)

500 USD

Municipality from budget

Issue together with re-registration of concessions and tender documents for new concessions a set of development guidelines/building codes, including a topographical site map (scale 1:2000 ) showing building restrictions such as building lines, etc.

2.6

Short term (3 months)

Development Agency reporting to municipality for decisions

2 000 USD

Concessionaires and municipality

Develop tender documentation for the calling of bids for concessions on land becoming vacant through the process described in B5 above, in order to secure sufficient contribution towards development costs by concessionaires. (The value of land should be used as a basis to raise levies to provide funds for direct investment in development of the area (e.g. operation of Development

2.7