DEMONSTRATION ACTIVITIES – Xai-Xai IDP

FAO-PAP/RAC-MICOA

TIMEFRA ME

RESPONSIBLE ORGANISATION

government

ESTIMATED COST (where available)

FINANCED

BY concessionaires

ACTION

STEP

Short term

Cost of internal roads, pedestrian paths, and public parking areas:

(12-24 months)

160 000 USD 340 000 USD

Grading and stabilising only (Initial phase); and

Paving and concrete stormwater channels.

Short term

(12-24 months)

Development Agency and Electricity company with contractors, supervised by government

To be provided by electricity company

Electricity company to define

Electrification of Praia Velha:

Share of bulk supply (sub-stations, supply lines, etc.) Street lighting and lighting of common areas Internal reticulation (domestic supply) Individual connections

2.11

Short term

Sewage disposal

2.12

(12-24 months)

Individuals supervised by government

1 200 USD/lot

Individual concessionaires

Initial phase: Individual septic tanks and small disposal and treatment systems

Medium to long term

Development Agency and contractors supervised by government

Pre-financed by bank loan and recovered from concessionaires

Upgrading to complete municipal disposal and treatment system