In LDM notation, relationships are viewed as connecting a) two nodes, b) an embedded node (embed) and a node, or c) two embeds, making relationship types no longer relevant.  For instance, depending on activity positioning, FS and SS relationships will graphically appear in LDM as follows:

Finish-to-Start (FS) and Start-to-Start (SS) Logic on LDM Notation

Planning and Scheduling Consolidate Into One and the Same Process

With GPM, once an activity is positioned or re-positioned on planned dates, floats in the evolving plan instantaneously calculate without the necessity of a conventional CPM backward pass.  In this respect, GPM is a networking process of one-step flow, instead of a flow consisting of batches [5].    Allowing for individual preferences [6], batching in CPM may break down as follows: