Transient stability studies for major events like grid disturbances or other issues periodically or as and when requested by the constituent(s).

vi.

System studies related to transmission constraints.

vii.

Studies specific to high / low voltage conditions with specific reference to reactors or capacitors operation / requirement.

viii.

Identification of requirement of reactors as and when required

ix.

Co-relation of protection related issues from Studies as and when required

x.

To draw out the contingency plan of Delhi Power System.

xi.

Any other technical study referred by the GCC.

20.2 Composition of System Study Sub-Committee:

20.2.1General Manager (Planning) of STU shall be Chairperson of the System Study Sub-Committee and preside over the meetings.

20.2.2 Dy. G.M. (Planning) of STU entrusted with the system study shall be convener of this Sub- Committee.

20.2.3System Study Sub-Committee shall be represented by the Members of the GCC constituents at the level of Executive Engineers / Managers familiar with the subject.

20.3 Meetings:

The meeting will be held quarterly or as and when required to address the issues of urgent nature.