PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT) - page 6 / 9

78 views

0 shares

2 downloads

0 comments

6 / 9

Node

Duration

ES

EF

LS

LF

Slack

A

12

0

12

2

14

2

B

9

0

9

0

9

0

C

10

12

22

14

24

2

D

10

9

19

9

19

0

E

24

9

33

35

59

26

F

10

12

22

53

63

41

G

35

22

57

24

59

2

H

40

19

59

19

59

0

I

15

12

27

48

63

36

J

4

59

63

59

63

0

K

6

63

72

63

72

0

The earliest start time, earliest finish time, latest start time and latest finish time for each activity are calculated in the following table: