Train arrives and stops at S 35.

S 39-danger

Track

after

the

S/A – 506 clear overlap of S 1 will

S-35-danger.

be blank.

Setting the route for ‘RAJDHANI’

The procedure followed to set the route for RAJDHANI is same as that followed in the second condition.

Other important criteria’s

  • a)

    Trap 105 should be Open.

  • b)

    SH 5, SH 44, S16 should be ON.

c)

  • i)

    Points 101-102 normal.

  • ii)

    Points 102-108-normal.

  • iii)

    Points 111-112 normal

Simulation 4:(Continuation from third condition)

The goods train on the loop line has developed a loco failure. Hence arrangements

are made for a relief engine by TLC (Traction Loco Controller) BDTS (Bandra Terminus) loco shed.

which comes from

Conditions are same as for the Rajdhani case, only that the loco doesn’t cross S/A 506 (The Advance Starter).The loco stands at 39 AT. After this SH – 44(green button) and DGL (black button) are pressed together.

Thus the four conditions are established by the help of a visual display on a signal panel with the help of the monitoring system.

44