SOLID WASTE PROCESSING AND DISPOSAL

CHAPTER 1200-01-07

(Rule 1200-01-07-.02, continued)

    • (ii)

      Take such action as he deems appropriate pursuant to that paragraph.

  • 4.

    The permittee may not initiate construction and/or operation unless and until authorized by the Commissioner in writing.

(3)

Processing the Permit

(a)

Preliminary Notices - Within 30 days after the date of receipt, the Commissioner shall issue a preliminary public notice under subparagraph (e) of this paragraph for each Part 1 permit application received.

(b)

Review of the Permit Application

1.

The Commissioner shall review every permit application for completeness. Upon completing the review, the Commissioner shall notify the applicant in writing

whether the application Commissioner shall list

is complete. If the application is the information necessary to make

incomplete, the the application

complete. The complete upon completed, the

Commissioner receiving the

Commissioner

shall notify the applicant that the application

required

information.

After

the

application

may

request

additional

information

from

is is

an

applicant but only when necessary to clarify, modify, or supplement submitted material. Requests for such additional information will not application incomplete.

previously render an

    • 2.

      When the Commissioner decides that a site visit is necessary for any reason in conjunction with the processing of an application, he shall notify the applicant and a date shall be scheduled.

  • (c)

    Draft Permits

  • 1.

    Once an application is complete, the Commissioner shall tentatively decide whether the permit should be issued or denied.

  • 2.

    If the Commissioner tentatively decides the permit should be denied, he shall prepare a notice to deny. A notice of intent to deny the permit shall be sent to the applicant. The applicant may wish to appeal the Commissioner’s decision to the Board by filing a written petition as provided at TCA 68-211-113(b) of the Act.

  • 3.

    If the Commissioner tentatively decides the permit should be issued, he shall prepare a draft permit as set forth in part 4 of this subparagraph.

  • 4.

    A draft permit shall contain (either expressly or by reference) all applicable terms and conditions from paragraph (4) of this rule.

    • 5.

      All draft permits shall be subject to the procedures of subparagraphs (d), (e), (f),

      • (g)

        , (h), and (i) of this paragraph, unless otherwise specified in those subparagraphs.

  • (d)

    Fact Sheets

1.

A fact sheet shall be prepared for every draft permit (or notice to deny the permit).

2.

The fact sheet shall briefly set forth the principal facts and the significant factual, legal, methodological and policy questions considered in preparing the draft permit to include, when applicable: