FEE2006 Perugia May 2006

Philippe Farthouat, CERN

Experience from the past: Path from TDR to Completion

Conclusion from this: we should have TDR in 2008

Later would shift the completion date away from 2015

But 2008 is too early for getting sufficient data from LHC

TDR will be later than 2008

The ID upgrade has to be done faster than the present ID was done

Limited time for fundamental detector R&D

Ref: talk of Tyndel at Genova tracker upgrade workshop

http://agenda.cern.ch/fullAgenda.php?ida=a053875

Installation

Commissioning

Integration

Sub-assemblies

Modules

Parts (sensors, ASICs, Opto…)

TDR

7

6

5

4

3

2

1

0

Pre-series

Production