Proposed Schedule MGA has mapped out a focused accelerated 16-week schedule that is attached. Included in it are two charrettes and two public presenta- tions. This time period provides West Windsor Township with the op- portunity of completing additional tasks and developing and adopting an implementing ordinance within the 18-month period allocated for the Redevelopment Plan effort.

The schedule includes a concentrated two-week charretting period in which the community and the planning team participate in the planning process. This type of charrette is typical of the charretting methodology utilized by DPZ and is explained further in Section 6. Public Presentation Techniques.

A determination of the preferred schedule should be made in accor- dance with the preferences of West Windsor Township Officials. We would expect this to be a key item of discussion at the Project Kickoff.

MICHAEL GRAVES & ASSOCIATES with DUANY PLATER-ZYBERK AND COMPANY

Document info
Document views360
Page views360
Page last viewedMon Dec 05 09:53:30 UTC 2016
Pages144
Paragraphs1135
Words41934

Comments