Transportation and handling

Prior to unloading of pipes from trailers, all items shall be inspected for any visual/transportation damages.

From the lay-down area to the trench site, the pipes shall be transported through trailers or by using of Hydra.

Single   pipe   must   be   unloaded   and   handled separately (one at a time) by using pliable straps, wide fabric straps, slings or ropes to lift single pipe. (Not using Steel Cables or Chains).

Individual pipe can usually be lifted with a single sling.

At  any  time  during  handling  or  installation  of  the pipe,  any  damage  such  as  cracks,  de-lamination  or fracture  occurs,  the  pipe  should  be  repaired  before the section is installed.