Presentation Title

WVSSII Contract Milestones

Completed Tasks:

NOAA Solicitation:  August 2006

Contract Award to ARINC/SSI/SWA:  June 2007

Critical Design Review:  March 19, 2008

Parts Ordered:  June 1, 2008

Government Chamber Tests:  July and September, 2008

Production Readiness Review:  October 28, 2008

Future Milestones:

Receive Special Type Certificate (STC) and Parts Manufacturing Authority (PMA) for B-737, B-757:  March 2009

Production Run: Build/Test 80 WVSSII units:  March 2009

Install 31 WVSS II on Southwest B-737: April-June 2009

Replace 25 WVSSII on UPS B-757:  April-June 2009