CSC444 Lec03 12

Suggested metrics

Plot planned and actual staffing levels over time

Record number & type of code and test errors

Plot number of resolved & unresolved problem reports over time

Plot planned & actual number of units whose V&V is completed over time:

a) design reviews completed

b) unit tests completed

c) integration tests completed

Plot software build size over time

Plot average complexity for the 10% most complex units over time

(using some suitable measure of complexity)

Plot new, modified and reused SLOCs for each CSCI over time

SLOC = Source Lines Of Code (decide how to count this!)

Plot estimated schedule to completion based on deliveries achieved

(needs a detailed WBS and PERT or GANTT chart)

Source: Adapted from Nusenoff & Bunde, 1993

© 2001, Steve Easterbrook