Tool 2: PERT charts

1

2

3

4

5

6

7

8

0

10

9

te=6

te=4

te=11

te=6

te=2

te=9

te=4

te=0

te=7

te=7

te=9

te=1

te=3

Notation

Nodes indicate milestones

Edges indicate dependencies

Edges are labelled with time to complete

Shows Critical Path

Longest path from start to finish

any slippage on the critical path will cause project delay

Source: Adapted from Blum, 1992, p439

see also: van Vliet pp193-6