STUDENT’S NAME: BINAMRA PAUL SOY

Project Title: Reducing the delays in the Pre-Production activities

Project Guide:Mr.Bikas Agrawal

Background: It is important to note that the pre-production process networks are unique for every single enterprise., every single buyer and even for every single order. In the absence of a standardized pre-production process network, elimination, concurrence and integration approach will be too specific to be applicable across industry. Based on this the project is undertaken to explore generalized or standardized solutions/techniques that can be applied.

Objective:To successfully trace out the reasons of delays in the pre-production activities, and finding solutions to these problems.

Methodology:Detailed study of the department concerned with the pre-production activities, personal observations, questionnaire and interviews.

Findings:Pre-production activities sheet developed for different lead time category and a master sheet was developed for PPC department for auto generation of planned dates.

Conclusion: This project helped to face the practical challenges in the industry and gave me a deeper insight of the complete business process.