Semi Annual Report

10/31/01 4/1/02 4/1/01

5

Prototype Testing & Refinement

7/15/02

6

Attend Annual Review

N/A

N/A

7 8

Preliminary Production Design

4/15/02

6/20/02

Benefits Update & Conclusions

7/15/02

7/30/02

9

Final Report

6/15/02

8/30/02

Milestone/Task Title

Final Mile- stone

Original/ Previously Planned Completion Date

8/31/02

  • +

    non-billed wrap-up 8/31/02

    • +

      non-billed wrap-up

to 11/30/02 11/30/02

RSV

RSV

Revised

Actual

Responsible

Planned

Completion

Organization

Completion

Date

10/31/01 4/1/02 8/31/02

  • +

    non-billed

wrap-up N/A

8/31/02

RSV

RSV

RSV

RSV

Date

Completed with no charge to DOE.

$11,360/ $12,265

$8886/ $8731

$3930.33/ $6806.75

Test plan completed. Refined design has been built and tested and data recorded.

Included in task 8 $6,240/ $6,740

--

--

N/A

$2442/ $3255

$539/ $721.

A preliminary production design has been completed and documented.

$2,480/ $3,280

$1765/ $2335

$1462.33/ $3037.67

Benefits have been updated and conclusions have been documented.

Included in task 8

--

--

A Final Report has been prepared and is being sent to the DOE.

$40000.00/ $46821.42

Original

Revised

Actual

Projected

Projected

Completed

Cost

Cost

Cost

(Fed/

(Fed/

(Fed/

Non-Fed)

Non-Fed)

Non-Fed)

Milestone Notes

Page 45

November 24, 2002

Document info
Document views183
Page views183
Page last viewedMon Jan 23 08:48:13 UTC 2017
Pages49
Paragraphs647
Words7715

Comments