Total of 8 contracts worth S$302 million First two contracts completed Remaining 6 contracts:

Project

Expected Completion Date

South Podium

End September 2009

North Podium

End November 2009

ArtScience Museum

End January 2010

View Corridors & Canopies

End January 2010

Lion Garden Bridge & Cooling Tower Structure

End January 2010

SkyPark

End January 2010