Deficiency Map

Map shows the roadway and intersection areas that do not meet the recommended illumination levels from the ANSI standard.

Approximately 36% (47 of 132) of the roadways are deficient.

Approximately 56% (39 of 70) of the intersections are deficient.

Master Plan

All new decorative street lights in the CBD are recommended to be installed and maintained by AEP

The City will install decorative lighting fixtures  on top of traffic signal poles to meet the lighting requirements at intersections.

Master Plan Cost Estimate

City of Laredo Master Street Lighting Plan

Item Description

Install Quantity

Unit Install Cost (2008 Dollars)

Grand Total

175W MH Granville Decorative Fixture

543

$835.11

$453,464.93

14’ Metal Street Light Pole

543

$2,250.08

$1,221,790.91

Single Mast Traffic Signal Pole With Top Mounted Washington 400W MH Fixture

137

$11,279.02

$1,545,225.06

Concrete Base For Traffic Signal Poles

137

$3,080.86

$422,077.55

Bore 2 Inch, 2 Inch Conduit, and #6 TPXU

88,000

$35.23

$3,100,308.24

Grand Total

$6,742,866.69

Master Plan Summary

543 Decorative Street Lights

137 Traffic Light Poles with Decorative Fixtures

88,000’ of Lighting Wire

Phased Implementation

The implementation of the Master Street Lighting Plan can be easily broken up into small projects

It is recommended that the areas with existing lighting deficiencies be addressed first.

Replacement of existing cobrahead lights can be accomplished at a later date.

Prescriptive Plan Cost Estimate

City of Laredo Prescriptive Street Lighting Plan

Item Description

Install Quantity

2008 Material

Unit Install Cost (2008 Dollars)

Grand Total

175W MH Granville Decorative Fixture

193

$649.00

$835.11

$161,176.30

14’ Metal Street Light Pole

193

$1,283.54

$2,250.08

$434,264.54

Single Mast Traffic Signal Pole With Top Mounted Washington 400W MH Fixture

79

$8,500.00

$11,279.02

$891,042.19

Concrete Base For Traffic Signal Poles

79

$2,000.00

$3,080.86

$243,387.78

Bore 2 Inch, 2 Inch Conduit, and #6 TPXU

21,750

$1.65

$35.23

$766,269.37

Grand Total

$2,496,140.18