remediation system. Supervise installation of system Design product collection, demulsivication, and biological treatment unit Supervise building, installation and operation of same

Ampol / Mobil / Shell / BP

carry out approx. 70 ESA's on service stations design, plan and supervise approx. 40 on-site soil remediations of service station (demolish & auction)

BP The Netherlands

Further Investigation of Soil and Groundwater; Design of an In-situ Bio Remediation System for Groundwater and Soil

Q8 The Netherlands

Cost Evaluation of Remediation Alternatives; Design of an In-situ Bio Remediation System for Groundwater and Soil

Texaco Benelux

Investigation of Soil and Groundwater; Supervising Excavation; Risk Assessment

Texaco Benelux

Investigation of Soil and Groundwater; Risk Assessment

BP Benelux

Further investigation of Soil and Groundwater

outlet North Melbourne

Australia

Zwolle

Rolde

Dudelange

Cote d'Eich

Rodange

1994 Arnhem

Texaco for AVEBE bv

In-situ respiration test Determination of heterogeneity of soil Design in- situ installation for placement under basement of apartment flat Design and experimental construction of sliding side-doors in air injection filters to allow air in-take level to be regulated (from 11 to 4 m b.g.l.) Realisation of remediation in 1 year

Ogden, Utah US

Hill and other AFB

Seconded to Battelle Bioresearch Group, assisted with on-site measurements (Airforce Bioventing Initiative / Natural Attennuation) at aircraft fuel supply and marine support facilities

Sydney Airport

Caltex

Design of very large 500 well free product recovery system on depot/retail site (aircraft filling) Supervise implementation, Tuning of extraction rates, and on-going site investigation (continuous coring to quantify volume per 2" soil layer) to assess volume to be recovered Design and Patented special fully pneumatic automatic hydrocarbon recovery system (MPRS)

Trail Bay, NSW

Caltex

Oil terminal facility investigation of groundwater plume (through layered and fractured rock) and nearby (200 m) river bed where contaminated groundwater emerged Risk assessment studies Risk

1993