was Jo-Med Construction with a bid of $258,650.  The only other bid received was from Adamsville Maintenance in the amount of $402,964.  HMM’s Engineers estimate for the work was $311,500.  Jo-Med Construction will sub-contract the manhole grouting and patching to NEPCCO who has satisfactorily completed work under the first rehabilitation project for the BTSA.  HMM has limited experience with Jo-Med Construction, however their experience to date has been satisfactory.  HMM feels that the BTSA has obtained a favorable bid for the work.  The work in general includes grouting and patching of defects in sanitary sewer manholes; repairing sanitary sewer manhole risers; partial excavation and replacement of sanitary sewers; partial excavation and installation of repair clamps on sanitary sewer defects; and spot excavation and replacement of private building service connection fittings and appurtenances.  The work is required to be completed in 120 calendar days from notice to proceed with the exception of final pavement restoration.

Phosphorous Pilot Study –  HMM has incorporated the revisions discussed with the BTSA to the report for the work under Task 1 evaluation of temporary and permanent facility alternates for assistance with the phosphorous reduction demonstration trials.  The temporary and permanent alternatives including their costs and schematic plans and process diagrams of the various alternative facilities and chemicals recommended will be provided to the BTSA within the week for review.  

OPERATOR’S REPORT – NOVEMBER 2007 (reporting on October 2007 activities)

Mr. Bowlby informed the Authority of the following:

BTSA crews TV’d 25 Roads (Allen Street, Appletree Lane, Birch Drive, Cherry Lane, Crier Court, Dayton Street, East Allen Street, East Craig Street, Ellis Drive, Fieldstone Drive, Fieldview Drive, Frederick Court, Hillside Terrace, Juniper Way, Lee Place, Manchester Drive, Monroe Place, Ridge Street, Shepard Way, Stonehedge Drive South, Sunnybrook Road, Walnut Circle, West Craig Street, Wildwood Drive & Woods End)

BTSA crews jetted 12 Roads (Allen Street, Birch Drive, Dayton Street, East Craig Street, Ellis Drive, Frederick Court, Hillside Terrace, Lee Place, Monroe Place, Prospect Avenue, Sunnybrook Road, West Craig Street).  

BTSA crews TV’d 3 laterals: 17 East Allen Street (Broken cleanout cap), 63 Juniper Way (root intrusion) & 3287 Valley Road (paint can in riser).  

BTSA crews responded to (3) blockages: 151 Bernards Drive (Water main break), 3287 Valley Road (Spray can of paint stuck in lateral), 17 East Allen Street (Homeowner drove over neighbor’s cleanout and busted it. She will repair it).  

BTSA crews inspected lateral capping at 534 Lyons Road & 60 Overlook Avenue.  

BTSA crews replaced two water lines on Vac-Con.  

BTSA crews exercised plant and station generators.   

BTSA crews replaced heating recirc pump #3.  

BTSA crews calibrated influent & effluent flow meters.

BTSA crews changed oil in vehicles.   

BTSA crews greased and changed oil in plant equipment.  

BTSA crews performed grease trap inspections.  

BTSA crews continue to meet permit parameters without any problems.

CPR & AED training was performed.

BTSA crews attended Work Place Harassment Training.  