ODOT Procurement Office - Construction

8

Oregon Department

of Transportation

Progression from Bid Opening to Notice to Proceed

Bid / Price Analysis /Review (7 days)

Notice of Intent to Award (3 day Protest Period)

Award Approval (3-4 days) -ODOT Deputy Director, OTC, FHWA  

Notice to Proceed

Rejection of individual bidder

Unresolved issues i.e. permits, agreements, personal services, etc.

Bonding, Insurance, execution of contract.

(1 - 2 weeks)

Bid Opening

Bids 10% or more over  Engineer’s Estimate. Justification to award / Input from local agency / Regions

Confirmation of funding

Protests, Lawsuits