Planned Sewer Network

To Pretoria

BWLC

Development Consortium

|

CURRENT REALITIES

3.8 Sewer

The watershed that runs through the centre of Linbro creates two distinct drainage zones, draining to the Bruma Outfall in the west, and the Modderfontein Outfall in the north east.

The outfall sewers join downstream and drain towards the Northern Waste Water Treatment Works, which is operated by Johannesburg Water. The works were recently extended and has sufficient capacity to cater for the Linbro Park development as envisioned.

Link sewers, upgrades and internal reticulation will be required to connect the planned

developments to the infrastructure as indicated.

existing

outfall

The sewer reticulation system should not pose a constraint to future development. However, new development may also be restricted to commence closest to the connection points at the north-east, north-west and south-west outfall sewers.

LINBRO PARK: Urban Design Framework Plan

June 2010

17