5/4/05 Draft VI

Resource Management Plans for Trails/Routes Rated Fair or Poor Table 9 provides specific resource management plans for each trail/route rated fair or poor to bring each up to good specifications.

Table 9. Problems to be rectified to bring system components rated fair or poor into compliance (good rating) by trail/route, 2004.

Trail /Route

Management Unit(s)

Recommended Action(s)

UP Brevort-

Soo

Some areas need to be brushed to meet specifications.

Trout Lake Cycle Trail

Newberry- Rexton Cycle Trail

Newberry, Soo

Some areas need to be brushed to meet specifications

Silver Cr. Cycle Trail

Newberry

Poor job of brushing, some areas need to be brushed to meet specifications.

Norway ATV Trail

Crystal Falls

Numerous wet areas need reroutes or boardwalks. ORV users are doing reroutes by bypassing these areas, but a permanent reroute or boardwalk needs to be done in most cases. A portion of the trail that lies west of Norway Truck Trail (runs N/S) should be closed. Major damage is occurring in some areas and no options for reroutes in most locations. Predominantly rock and swamp. Possibilities do exist to use other two tracks and a portion of forest road to eliminate this poor trail mileage and replace it with comparable mileage of usable trail.

Pine Ridge ATV Trail Two Heart ATV Trail LP

Newberry

Newberry

Poor job of brushing, some areas need to be brushed to meet specifications. Some areas need to be brushed to meet specifications

Bummers Roost Cycle Tr.

Atlanta

MCCCT Cadillac

Cadillac Ranger District - FS

Meadows MCCCT Red Bridge Cycle Tr. Atlanta

Mio Ranger District -FS Gaylord

Atlanta

Poor signage. Needs more and appropriate confidence markers and stops. Needs better brushing, especially in front of signs. Need to restore some erosion along road crossings and sandy areas. A wet area north of Boon Rd. needs to be improved. Plans being made to make this improvement as part of a timber sale. Need for erosion control and additional brushing.

Signage is poor. Need more confidence markers, directional arrows, begin and end signs and stops. Needs additional brushing. Reroutes need to be put back

28