Clearwater Oil Company, Ltd.

Big Bear Lease No. 2 Production Facility

SAMPLE Spill Prevention, Control, and

Countermeasure (SPCC) Plan

APPENDIX G: Equipment Shut-off Procedures

Source

Action

Manifold, transfer pumps or hose failure

Shut in the well supplying oil to the tank battery if appropriate. Immediately close the header/manifold or appropriate valve(s). Shut off transfer pumps.

Tank overflow

Shut in the well supplying oil to the tank battery. Close header/manifold or appropriate valve(s)

Tank failure

Shut in the well supplying oil to the tank battery. Close inlet valve to the storage tanks.

Flowline rupture

Shut in the well supplying oil to the flowline. Close nearest valve to the rupture site to top the flow of oil.

Flowline leak

Shut in the well supplying oil to the flowline. Immediately close the nearest valve to stop the flow of oil to the leaking section.

Explosion or fire

Immediately evacuate personnel from the area until the danger is over. Immediately shut in both wells if safe to do so. If possible, close all manifold valves. If the fire is small enough such that it is safe to do so, attempt to extinguish with fire extinguishers available on site.

Equipment failure

Immediately close the nearest valve to stop the flow of oil into the leaking area.

-X-

Version 1.0, 11/28/2005