its 29th session (Durban, 2005) the mission noted that the management plan conforms with the new Law of the Republic of Belarus on the Protection of Historical and Cultural Heritage, passed on 24 July 2006. The plan does not however include a policy for restoration and reconstruction, as requested by the Committee.

  • j)

    The mission considered that in view of the enormous tasks of protecting and conserving the Belarusian monuments and sites, the Department of Protection of Historical and Cultural Heritage and Restoration should increase its staff of specialists in conservation, restoration and documentation.

  • k)

    The mission noted that proposals were being drawn up for installing heating in the Corpus Christi Church and considered that an overall conservation plan would be needed before this work was undertaken. It further noted the need for greater protection to the urban setting of Nesvizh, where in the past few decades new buildings have been erected that are out of scale with the urban grain and impact adversely on the visual integrity of the setting of the property.

The World Heritage Centre and the Advisory Bodies express concern at the demolition of the Eastern Gallery for structural reasons in the light of the fact that details of this project were not notified to the World Heritage Centre, for review by ICOMOS, in accordance with the Operational Guidelines, in order to allow discussion on whether further advice on structural engineering might have been provided. They nevertheless consider that the approaches to its rebuilding were adequate.

They note that the mission was generally satisfied at the approaches to restoration in terms of research, materials, techniques and documentation but that restoration and renewal seem to be inextricably intertwined without a clear rationale for their differing justifications. Although a Management Plan has been prepared for the property and accords with national law, this does not set out a clear approach for restoration, conservation and renewal as requested by the World Heritage Committee. Such a clear approach needs to be put in place before work projects are undertaken such as for the installation of heating in Corpus Christi Church.

Draft Decision 34 COM 7B.78

The World Heritage Committee

  • 1.

    Having examined document WHC-10/34.COM/7B.Add,

  • 2.

    Recalling Decision 33 COM 7B.93 adopted at its 33rd session (Seville, 2009)

  • 3.

    Acknowledges the results of the joint World Heritage Centre / ICOMOS reactive

monitoring mission of February 2010;

  • 4.

    Deeply regrets the demolition of the Eastern Gallery and its rebuilding without prior information being submitted to the World Heritage Centre, for review by ICOMOS, in accordance with Paragraph 172 of the Operational Guidelines,

  • 5.

    Requests the State Party to update the Management Plan clearly setting out approaches to conservation, restoration and renewal, in particular concerning rehabilitation and modernisation works;

6.

Urges the State Party to develop an overall conservation approach for the restoration of Corpus Christi Church and the installation of heating, including the advice of experts

State of conservation of World Heritage properties inscribed on the World Heritage List