Previous Committee Decisions 30 COM 7B.38 ; 31 COM 7B.51 ; 32 COM 7B.50

International Assistance Total amount provided to the property: 2007, USD 30,000, Technical Cooperation

UNESCO Extra-budgetary Funds Total amount provided to the property: USD 110,000 (Italy Funds-in-Trust); USD 23,100 (Croisi Europe); USD 86,900 (European Commission)

Previous monitoring missions 2002, 2005: World Heritage Centre missions; 2006: World Heritage Centre/ICOMOS/ICCROM Reactive Monitoring mission

Factors affecting the property identified in previous reports

  • a)

    No management and conservation plan;

  • b)

    Pressure from urban development;

  • c)

    Deterioration of dwellings;

  • d)

    Waste disposal problems;

  • e)

    Encroachment of the archaeological sites.

Illustrative material http://whc.unesco.org/en/list/116

Current conservation issues:

In response to Decision 32 COM 7B.50, the State Party submitted a state of conservation report, on 22 March 2010. This report provides information of progress achieved in the fields of management and conservation, and makes particular mention of the following activities:

a) State of conservation of architectural heritage

The report noted that the property continued to suffer changes as regards its buildings. As already emphasized in its 2008 report, the recent report again indicates that the reason for these changes is essentially due to the modification of the original plans of the houses because of new needs for comfort and the increase in the size of some family cells, the escalation in cost of the materials used for traditional livelihood (rice and millet, baobab fruit, shea butter), to the introduction of inappropriate solutions using cement and terra cotta, the abandonment of numerous buildings that have fallen into ruin, and the appearance of new constructions in the inscribed periphery. In the face of these changes, the Cultural Mission has questioned the contraveners and called upon the cooperation of the municipal and administrative authorities. But clearly, and according to the report, the involvement of these bodies is not yet fully secured for the task of protection assigned to the Cultural Mission of Djenné. The report also indicates efforts of collaboration with actors such as the corporation of masons « Barey Ton », the Djenne Heritage Association, the Association of Guides, the customary authorities and opinion leaders. Exemplary restoration has been carried out in 2009-2010. The Djenné Mosque has been restored in the framework of a Programme for the rehabilitation of Earthen Architecture, established between the Mali Ministry of Culture and the Aga Khan Foundation for Culture.

In the framework of the World Heritage Earthen Architecture Programme, a number of activities is also being implemented since January 2010 at Djenné including a rehabilitation project for the Youth House, financed by the Government of Italy, and the preparation of town planning and construction regulations adapted to earthen architecture. This project will enable the production of a technical guide for the rehabilitation of earthen architecture to assist in the control of interventions at the property and in its buffer zone.

The World Heritage Centre and the Advisory Bodies note the absence of clear working tools (town planning and construction regulations) to control the growth of new constructions and

State of conservation of World Heritage properties inscribed on the World Heritage List

WHC-10/34.COM/7B.Add, p. 84

Document info
Document views566
Page views566
Page last viewedSun Dec 04 06:56:20 UTC 2016
Pages206
Paragraphs4734
Words99190

Comments